After last month's auger fail, and realizing that where we had planned on setting posts was a massive layer of bedrock about 6"-12" below the topsoil, we made some real progress yesterday. A couple weeks agao, I had the idea to try using a rock bar to break up the rocks in the holes. I wasnt even sure if that would work, but since we had exhausted every other option I was willing to give it shot. To my suprise, it actually worked, and worked quite well. I was able to get these two holes dug, and the post set. Took about 3 hours of digging through solid rock, but I had made progress.
See Shannon's post for the pics...
Fast foward to this past Sunday. With a renewed life in project, we went out Sunday, and got quite a bit done before the weather closed in on us. Yes that's snow in the end of March. Finally preliminary ladder bridge framing has begun!
Here's the pics.
AWSOME GUYS !! THANK YOU FOR YOU HARD WORK MAN